A typical situation on a precast concrete project: the task for the connections between precast elements — walls, slabs, columns, beams — has already been sent to Allplan, the detailer is working on it, and then the architect changes a storey or the construction phases. The structure is reanalysed, and forces change in hundreds of connections. Reissuing the whole task means the detailer has to check everything from scratch.
We wrote a script that sends to Allplan only the connections that really need strengthening.
How the script compares two versions
The input is two exports from the connection design software, before and after the reanalysis. After a reanalysis, surface numbers in the model may shift and some connections may be regrouped. Comparing by numbers would give a false picture, so the script matches connections by geometry — by the position of the joint line in space. Supports on foundations are compared as groups of connections lying on shared lines. Without this, a single group alone can show over a dozen false “new” connections.

Both runs must use the same detail settings. Otherwise the difference mixes the change in the structure with a change in the catalogue.
What goes into the task
- Connections where the resultant force grew by more than 10%, or the number of parts increased.
- The statuses “new”, “decrease” and “gone” are recorded in the report but not sent to the task.
- Each connection in the IFC gets a label with a revision line “REV. A” and the date, so the detailer sees at once what changed.
- A new version of the task adds only the changes and does not overwrite edits already made in the model by hand.

Result
The detailer receives a small IFC with only the changed connections instead of a new task for the whole building. Checking is limited to the changed connections, and manual edits are not lost. If the structure on your project changes while detailing is already under way, contact us.